What construction actually costs in Kenya, item by item

A dated price list for materials, labour, services and professional fees, adjusted for where the lorry has to deliver. Free to read, free to reuse, and updated every quarter.

Version 2026.08Reviewed August 202655 items8 countiesCC BY 4.0
Read this first. These are indicative market ranges, not quotations. Prices in Kenyan construction move with fuel, with the shilling and with the season, and two suppliers in the same town will quote differently on the same day. Use this to check whether a quote you have been given is anywhere near the market, then get the quote in writing.

Materials cost what they cost standing on your plot, not in a Nairobi yard. Changing this adjusts every figure for haulage.

Nanyuki and Laikipia. Our base. Stone comes from the Laikipia and Meru quarries, sand mostly from the Ewaso Ng'iro and Timau side. Cement and steel come up from Nairobi or Nakuru, which is the main reason materials here sit a little above Nairobi yard prices.

Cement, sand and aggregate

Cement, sand and aggregate prices in Nanyuki and Laikipia
ItemUnitLowTypicalHigh
Cement, 50kg bagCheapest bought by the full lorry rather than in tens. Do not buy more than about six weeks ahead, cement has a shelf life and hardens in the bag.bagKES 650KES 780KES 900
River sandPriced by distance from the river more than anything else. An 18 tonne lorry delivered around Nanyuki typically runs KES 30,000 to 45,000 including county cess.tonneKES 1,600KES 2,200KES 2,900
Ballast, crushed stoneAn 18 tonne lorry usually lands between KES 27,000 and KES 34,000. Check the size before you accept a load, oversize ballast wastes cement.tonneKES 1,500KES 1,900KES 2,500
HardcoreCompaction matters more than the stone. Hardcore laid in one thick layer and not compacted is the commonest cause of a cracked ground slab.tonneKES 900KES 1,300KES 1,800
MurramUsed for access roads and backfill. Widely available across Laikipia.tonneKES 700KES 1,100KES 1,600

Steel and reinforcement

Steel and reinforcement prices in Nanyuki and Laikipia
ItemUnitLowTypicalHigh
Deformed bar, Y12Steel tracks the global market and moves faster than anything else on site. Buy the whole structural requirement in one order if you can.length of 12mKES 1,150KES 1,350KES 1,600
Deformed bar, Y16length of 12mKES 2,000KES 2,400KES 2,850
Reinforcement steel, by weightHow engineers and quantity surveyors price it. Useful for checking a supplier quote against the market.tonneKES 95,000KES 108,000KES 125,000
BRC mesh, A142For ground slabs and screeds.rollKES 9,500KES 12,000KES 15,000
Binding wirekgKES 180KES 230KES 300

Walling and blockwork

Walling and blockwork prices in Nanyuki and Laikipia
ItemUnitLowTypicalHigh
Machine cut stone, 6 by 9 inchThe standard wall in this region. Price depends on the quarry, the size and how far the lorry travels. Ask for the cess receipt, it should come with the load.pieceKES 20KES 30KES 42
Machine cut stone, 9 by 9 inchUsed for boundary walls, retaining walls and thicker external walls.pieceKES 35KES 48KES 65
Concrete block, 6 inchFaster to lay than stone and often cheaper where there is no quarry nearby. Insist on blocks that have been cured properly, green blocks crack.pieceKES 65KES 90KES 120
Interlocking soil blockMade on site from soil and a little cement. Saves on mortar and transport, and works well on remote plots. Needs the right soil, so test first.pieceKES 45KES 65KES 90
Plaster sandtonneKES 1,800KES 2,400KES 3,200

Roofing

Roofing prices in Nanyuki and Laikipia
ItemUnitLowTypicalHigh
Box profile mabati, gauge 30The common budget choice. Gauge 30 is thin, and on an exposed Laikipia site the wind will find it. Gauge 28 is usually worth the difference.linear metreKES 480KES 560KES 680
Box profile mabati, gauge 28linear metreKES 550KES 660KES 800
Tile profile or versatile mabatiLooks like a tiled roof at a fraction of the weight, so the roof structure can be lighter.linear metreKES 620KES 780KES 980
Stone coated roofing tileQuieter in rain and much longer lasting. Needs a stronger roof structure, so price the timber with it.KES 1,200KES 1,900KES 3,200
Roof timber, 4 by 2 cypressBuy dry. Green roof timber twists and lifts the sheets within a season.foot runKES 55KES 75KES 100
Gutters and downpipes, PVCNot optional here. Roof water is the cheapest water you will ever get, and in Laikipia it fills a tank fast.linear metreKES 450KES 700KES 1,100

Timber and joinery

Timber and joinery prices in Nanyuki and Laikipia
ItemUnitLowTypicalHigh
Cypress timber, 6 by 1foot runKES 40KES 58KES 80
Solid cypress door and frame, fittedThe price gap between a dry door and a green one is small. The gap in how they behave after one dry season is not.eachKES 14,000KES 22,000KES 34,000
Mahogany door and frame, fittedMain entrance doors sit at the top of this range, especially double leaf.eachKES 28,000KES 45,000KES 85,000
Fitted wardrobeMeasured off the finished wall rather than the drawing, which is why ours have no filler strips.linear metreKES 18,000KES 28,000KES 48,000
Kitchen units, base and wallWorktop is priced separately. Granite and quartz are the usual jump in cost.linear metreKES 22,000KES 38,000KES 75,000
Timber panelled ceilingKES 1,800KES 2,800KES 4,500
Solid timber floor, laid and finishedMoisture in the screed is what ruins timber floors. It has to be dry before boards go down, and that is a programme decision, not a materials one.KES 3,200KES 5,000KES 9,000

Finishes

Finishes prices in Nanyuki and Laikipia
ItemUnitLowTypicalHigh
Floor tiles, suppliedKES 900KES 1,600KES 4,000
Tiling, laying onlyKES 350KES 550KES 900
Emulsion paint, 20 litrebucketKES 2,200KES 4,200KES 8,000
Exterior weatherproof paint, 20 litreAt 2,000m and above the sun is harsh. Cheap exterior paint fades in two years and you pay twice.bucketKES 6,500KES 9,500KES 15,000
Aluminium window, supplied and fixedKES 6,500KES 11,000KES 22,000
Steel casement window, supplied and fixedKES 4,500KES 7,500KES 12,000

Plumbing, electrical and water

Plumbing, electrical and water prices in Nanyuki and Laikipia
ItemUnitLowTypicalHigh
Borehole, drilled and equippedDepth to water decides this, and around Laikipia it varies enormously over short distances. A hydrogeological survey and the NEMA and WRA permits come first, and they are not optional.eachKES 900,000KES 1,600,000KES 3,000,000
Plastic water tank, 10,000 litreIncludes the base in most quotes but check. A tank on unlevel ground fails at the outlet.eachKES 78,000KES 95,000KES 125,000
Septic tank and soakpiteachKES 180,000KES 320,000KES 600,000
BiodigesterTakes less space than a septic tank and soakpit, which matters on a small plot or where the ground does not soak.eachKES 150,000KES 260,000KES 480,000
Solar system with battery, about 3kWEnough for lighting, sockets, a fridge and a pump on most family houses. Electric water heating and cooking are what push a system into the millions.systemKES 450,000KES 750,000KES 1,400,000
Solar water heater, 200 litreRequired by regulation on many new houses, and it pays for itself faster than any other single item here.eachKES 95,000KES 145,000KES 240,000
Electrical point, wired and fittedpointKES 1,800KES 2,800KES 4,500
Kenya Power connection, ordinaryCheap if a transformer is close, expensive if poles have to be run to your plot. Ask the neighbours before you assume.eachKES 35,000KES 60,000KES 180,000

Labour

Labour prices in Nanyuki and Laikipia
ItemUnitLowTypicalHigh
General labourerdayKES 500KES 700KES 900
Mason or fundidayKES 1,200KES 1,600KES 2,200
CarpenterdayKES 1,200KES 1,700KES 2,400
Steel fixerdayKES 1,300KES 1,800KES 2,500
Foreman or site supervisordayKES 2,200KES 2,900KES 3,800
Labour only, whole houseHow labour-only contracts are usually priced when the client buys materials. Roughly a quarter to a third of the total build cost.KES 9,000KES 14,000KES 22,000

Professional and statutory fees

Professional and statutory fees prices in Nanyuki and Laikipia
ItemUnitLowTypicalHigh
Architectural designThe BORAQS scale sets 6 percent as the minimum for full architectural service. A drawings-only package for a modest house is often quoted as a fixed fee instead.% of construction cost5%7%12%
Structural engineering% of construction cost1.5%2.5%4%
Quantity surveying% of construction cost1.5%2%3.5%
County plan approval, residentialEvery county sets its own schedule and charges by size and use. Laikipia is commonly quoted around KES 50,000 for a residential site. Confirm the current figure with the county, it changes with each finance act.eachKES 15,000KES 50,000KES 120,000
Soil investigation and testThe cheapest insurance in construction. A test costs a fraction of one cracked house.eachKES 35,000KES 65,000KES 150,000
Land survey and beacon settingeachKES 25,000KES 50,000KES 120,000
NEMA project report where requiredNeeded for larger developments, boreholes and anything near a river or conservancy.eachKES 60,000KES 120,000KES 350,000

Where these numbers come from

This edition is compiled from published Kenyan supplier price lists, industry cost guides, county finance schedules and the BORAQS scale of professional fees, reviewed in August 2026. Every figure carries a low, a typical and a high, because a single number would be a lie about a market this variable.

Regional figures are the base price adjusted by a haulage factor rather than separately surveyed. That is a simplification and we would rather say so than pretend to a precision we do not have. It is accurate enough to plan with and not accurate enough to order from.

The list is reviewed quarterly. The next review is due November 2026. Every past version stays in the public record, which over time turns this page into something more useful than a price list: a record of what building in Kenya has actually cost, year by year.

Sources for this edition

  • Published Kenyan supplier price lists (cement, steel, mabati, stone, timber)
  • Kenyan quantity surveying and construction cost guides, 2026 editions
  • Laikipia County finance schedules for approval and permit charges
  • BORAQS scale of professional fees

Use it in your own work

The whole price list is published as JSON. No key, no sign up, no rate limit, no tracking. If you are a quantity surveyor, a developer, a bank, a journalist or a student, take it and use it. All we ask is a link back, which is what the licence requires anyway.

GET https://timberstone.co.ke/api/prices/v1/latest.json    # everything, current edition
GET https://timberstone.co.ke/api/prices/v1/regions.json   # counties and their adjustment factors
GET https://timberstone.co.ke/api/prices/v1/rates.json     # cost per m² by finish level
GET https://timberstone.co.ke/api/prices/v1/index.json     # what is available, and the version
Licence
Creative Commons Attribution 4.0. Use it commercially, change it, build on it. Credit TimberStone Ltd and link to this page.
Format
Static JSON files served from the same domain. Cacheable, fast, and they will not disappear behind a paywall.
Versions
Each edition carries a version and a review date. Current edition is 2026.08.

Paid a different price? Tell us and it improves the list

Right now we publish what we see in the market and what we pay ourselves. The next step is to open it up, so anyone building anywhere in Kenya can check a price against what other people actually paid last month rather than against a national average that fits nobody.

If you have a recent receipt, delivery note or written quote, send us a photograph of it with the item, the county and the date. We will check it and it goes into the next edition.

What we publish

A range and a typical figure, with how many submissions sit behind it. Never your receipt, never your name and never the supplier you used.

What we check

Every submission is read by a person against the document before it counts. Anything we cannot verify is left out rather than averaged in.

What you get

A price list that tells you whether you are being quoted fairly in your county, which is something no national average can do.

Submissions are handled under the Data Protection Act 2019. We keep the document only long enough to verify the figure, we publish nothing that identifies you or your supplier, and you can ask us to remove a submission at any time.

Want these prices applied to your own plot?

We will come and look at the ground, then give you an itemised figure built from real supplier quotes rather than an average.